Compliance & Regulatory Status

Kalgoorlie Complex · 40 active obligations · Last verified 30 May 2026

Overall Compliance Score

76/ 100

Down 4 pts from last quarter

Obligations At Risk

6of 40

3 require immediate action

Audits Within 30 Days

4upcoming

Next: DMIRS — 8 June 2026

Open Breach Items

2active

TSF-3 + Discharge pH

Regulatory Obligations

12 of 12
Permit No.
Obligation
Authority
Pillar
Threshold
Current Value
Variance
Status
Next Audit
Actions
MLP-2019-0043Progressive Rehabilitation — Annual TargetDMIRS WALand≥ 200 ha/yr148 ha YTD-26%At Risk
8 Jun 20269d away
MLP-2019-0044Topsoil Stockpile ManagementDMIRS WALand≤ 5 yr storage3.2 yr avg-36%Compliant
8 Jun 20269d away
MLP-2019-0042Tailings Storage Facility — Max Fill LevelDMIRS WAWaste≤ 85%87.3%+2.3%Breach
15 Jun 202616d away
MLP-2019-0045Tailings Seepage — Downstream DetectionDMIRS WAWaste≤ 0.30 L/s0.42 L/s+40%Remediation
15 Jun 202616d away
WL-2020-1183Pit Dewatering Discharge pHDWER WAWaterpH 6.5–8.5pH 8.9+0.4%Breach
22 Jun 202623d away
WL-2020-1184Total Dissolved Solids — DischargeDWER WAWater≤ 2,000 mg/L1,840 mg/L-8%At Risk
22 Jun 202623d away
WL-2020-1185Groundwater Monitoring — Bore NetworkDWER WAWaterMonthly readingsMay readings complete0%Compliant
22 Jun 202623d away
HR-2022-0011Community Grievance Resolution SLAOECD Guidelines MonitorHuman Rights≥ 90% within 30 days72.3%-17.7%At Risk
30 Jun 202631d away
Showing 18 of 12 obligations

Upcoming Audits & Deadlines

Next 90 days · 7 scheduled

8 Jun 20269d

Progressive Rehabilitation Site Inspection

DMIRS WALand
15 Jun 202616d

Tailings Storage Facility Compliance Review

DMIRS WAWaste
22 Jun 202623d

Water Licence Conditions — Annual Review

DWER WAWater
30 Jun 202631d

Human Rights Due Diligence Submission

OECD MonitorHuman Rights
15 Jul 202646d

Air Quality & Dust Emission Reporting

EPA WACarbon
31 Jul 202662d

NGER Annual Greenhouse Gas Report

Clean Energy RegulatorCarbon
14 Aug 202676d

ESG Disclosure — Half-Year Report

ASX GovernanceAll Pillars